2000MW Coal-fired Power Plant Open Tender – Shortlisted bidders pursuant to Project 3B pre-qualification process
The Energy Commission has completed the evaluation of seven RFQ submissions and the following consortia have been shortlisted to participate in the tender exercise for the 2000MW Project 3B coal-fired power plant to be developed at their own site.
NO. | SHORTLISTED BIDDERS | LEAD MEMBER | PROPOSED SITE |
1. | 1Malaysia Development Bhd; and Mitsui & Co. Ltd. |
1MDB | Jimah, N.S.( Injection at Olak Lempit ) |
2. | Formis Resources Berhad, SIPP Energy Sdn Bhd, Posco Energy and Posco Engineering & Construction Co. Ltd. |
Formis | Tanjung Tohor, Johor.( Injection at Yong Peng East) |
3. | Tenaga Nasional Berhad, Global Power Ventures Sdn Bhd and China National Machinery Import & Export Corporation. |
TNB | Tanjung Hantu - Segari, Perak. ( Injection at Terong, Bruas ) |
4. | Malakoff Corporation Berhad and Sumitomo Corporation |
Malakoff | Pulau Carey, Selangor. ( Injection at Olak Lempit ) |
5. | YTL Power International Berhad and Ranhill Power Sdn Bhd. |
YTLP | Tanjung Tohor, Johor. ( Injection at Yong Peng East) |
RFP document is expected to be released on 23rd April 2013 and invitation letters will be issued shortly. The closing date for the Bid will be 30th September 2013.
All shortlisted bidders, including each member of the consortium, will be required to sign an Integrity Pact.
Energy Commission, 18th April 2013
- Open Tender for 2000 MW Coal-fired Power Plant Project 3B – RFQ participants responding to the pre-qualification process
- Coal fired power plant open bidding: Pre-qualification results for 1000MW Project 3A
- 1000MW and 2000MW coal-fired power plant projects
- Announcement: Coal fired power plant open bidding